Wrentham Housing Authority

Open bids and capital projects

Open bids and the projects in this authority's capital plan, with costs. Bids come from COMMBUYS; projects come from the annual plan the authority files with the state.

Open bids

None on COMMBUYS as of Sep 27, 2026. Get the free weekly email to hear when one posts.

Proposed for fiscal 2027 (5 projects, $909,848)

State fiscal year: July 2026 to June 2027. Available formula funding for the year, per the plan: $154,058. Proposals can run well past that; some depend on special awards from the state.

ProjectDevelopmentTotal project cost
Tub Surround Replacement 667-2
Kitchens & baths
Garden Lane$294,938
Tub Surround Replacements 667- 1
Kitchens & baths
Bennett Garden$181,500
Roof Replacement Building 14-18
Roofing & gutters
New Emerald Lane$49,295
Septic Study 667-1&2
Water, sewer & plumbing
Bennett Garden$43,804
Boiler Replacement- 15 Units
Heating, boilers & HVAC · special award requested: $340,312
New Emerald Lane$340,312

Proposed for fiscal 2028 (2 projects, $449,861)

State fiscal year: July 2027 to June 2028. Anticipated formula funding for the year, per the plan: $154,058. Proposals can run well past that; some depend on special awards from the state.

ProjectDevelopmentTotal project cost
SUST. Bathroom Fan Installation 667-1 & 667-2.
Heating, boilers & HVAC
$283,652
Switchgear and Transformer Replacement
Electrical & generators
Bennett Garden$166,209

Proposed for fiscal 2029 (1 project, $154,940)

State fiscal year: July 2028 to June 2029. Anticipated formula funding for the year, per the plan: $154,058. Proposals can run well past that; some depend on special awards from the state.

ProjectDevelopmentTotal project cost
Exterior Door Replacement
Windows & doors
New Emerald Lane$154,940

Further out: fiscal 2030–2031 (4 projects, $289,168)

The plan's “Years 4 and 5”: rough planning amounts, further out. State fiscal years: July 2029 to June 2031.

ProjectDevelopmentTotal project cost
Kitchen Cabinet, Counter & Sink Replacement Phase I
Kitchens & baths
Garden Lane$251,084
Shower Stall Replacement- #230 & #315 Garden Lane
Kitchens & baths
Garden Lane$28,648
VU24 Vacancy Turn Over Garden Lane
Unit turnovers & renovations
Garden Lane$9,436
ADA Egress Upgrades
Accessibility (ADA)
New Emerald Lane$0

Active projects (8)

The plan's list of projects already under way: some in design or out to bid, some under construction or wrapping up. When one goes out to bid, the COMMBUYS title is sometimes just its FISH number.

ProjectDevelopmentTotal project cost
AIP: 667 Routine Turnovers
FISH 350091
$13,200
Egress Concerns and Asphalt Replacement 667-1 & 2
FISH 350081
Bennett Garden$463,250
ARPA FF: Silcock Replacement 667- 1&2
FISH 350082
Bennett Garden$28,547
Fire Alarm Device Replacement 667-1 &2
FISH 350083
Bennett Garden$24,177
Kitchen Cabinet & Countertop Replacement - FORCE ACCOUNT
FISH 350086
New Emerald Lane$75,000
Accessibility Improvements
FISH 350092
Bennett Garden$57,290
Vacant Unit - Force Account
FISH 350094
Garden Lane$90,275
Shower Installations: Apt. 120 & 165
FISH 350095
Bennett Garden$91,481

Costs are total project costs (design and construction) as listed in the plan, read automatically from the PDF. The plans schedule work by the state's fiscal year (July to June), which can differ from an authority's own. Proposed projects are not funded until the state approves them, and plans change: costs rise, projects slip or get split into phases. Check the plan itself before relying on a number.