Plainbids · All housing authorities · Updated Sep 27, 2026

Wareham Housing Authority

Open bids and capital projects

Open bids and the projects in this authority's capital plan, with costs. Bids come from COMMBUYS; projects come from the annual plan the authority files with the state.

Open bids

None on COMMBUYS as of Sep 27, 2026. Get the free weekly email to hear when one posts.

Proposed for fiscal 2027 (4 projects, $967,191)

State fiscal year: July 2026 to June 2027. Available formula funding for the year, per the plan: $255,227. Proposals can run well past that; some depend on special awards from the state.

ProjectDevelopmentTotal project cost
Bathroom Exhaust Fans 667- 1/667-2
Heating, boilers & HVAC
$291,156
Phase 4 Window Replacement BLDG. F 667-2
Windows & doors
Redwood Park$249,999
Window Replacement BLDG. E 667-2
Windows & doors
Redwood Park$255,764
Boiler and Hot Water Heater Replacement Project - Merged
Heating, boilers & HVAC
$170,272

Proposed for fiscal 2028 (1 project, $197,955)

State fiscal year: July 2027 to June 2028. Anticipated formula funding for the year, per the plan: $255,227. Proposals can run well past that; some depend on special awards from the state.

ProjectDevelopmentTotal project cost
Cast Iron Drain Line Replacement Redwood Park
Water, sewer & plumbing
Redwood Park$197,955

Proposed for fiscal 2029 (2 projects, $290,384)

State fiscal year: July 2028 to June 2029. Anticipated formula funding for the year, per the plan: $255,227. Proposals can run well past that; some depend on special awards from the state.

ProjectDevelopmentTotal project cost
Hallway/Common Area Painting 667-2
Interiors, flooring & painting
Redwood Park$76,657
Kitchen Exhaust Fans 667-2
Heating, boilers & HVAC
Redwood Park$213,727

Further out: fiscal 2030–2031 (2 projects, $957,964)

The plan's “Years 4 and 5”: rough planning amounts, further out. State fiscal years: July 2029 to June 2031.

ProjectDevelopmentTotal project cost
Crawl space plumbing upgrades
Water, sewer & plumbing
Agawam Village$312,500
Maintenace Utility Building
Other
Agawam Village$645,464

Active projects (15)

The plan's list of projects already under way: some in design or out to bid, some under construction or wrapping up. When one goes out to bid, the COMMBUYS title is sometimes just its FISH number.

ProjectDevelopmentTotal project cost
AIP: 667 Routine Turnovers
FISH 317062
$20,800
Repair HP ramp
FISH 317010
$0
H/C Hand Rails Bldg 1
FISH 317035
Agawam Village$2,008
ARPA FF: Replace Sewage Lines - Redwood Park
FISH 317046
Redwood Park$273,190
Replace ACT in Community Center
FISH 317048
Agawam Village$53,403
Fire Alarm System Replacement (Main Panel Bldg. #1)
FISH 317052
Agawam Village$39,086
Boiler and Hot Water Heater Replacement Project
FISH 317053
Redwood Park$60,749
Boiler and Hot Water Heater Replacement Project
FISH 317054
Redwood Park$0
Community Building Roof Replacement Agawam Village
FISH 317056
Agawam Village$51,503
New Asphalt Walkways Building 1
FISH 317057
Agawam Village$11,271
Phase 3 Window Replacement - CDBG
FISH 317058
Redwood Park$423,885
Exterior Ramp Replacement
FISH 317059
Redwood Park$121,921
Redwood Park Exterior Main Entry Door Replacement
FISH 317063
Redwood Park$333,094
Asbestos Abatement 667-1
FISH 317064
Agawam Village$27,830
Vacant Unit Turnover 667-1 - Task Force
FISH 317065
Agawam Village$250,000

Costs are total project costs (design and construction) as listed in the plan, read automatically from the PDF. The plans schedule work by the state's fiscal year (July to June), which can differ from an authority's own. Proposed projects are not funded until the state approves them, and plans change: costs rise, projects slip or get split into phases. Check the plan itself before relying on a number.