Ware Housing Authority

Open bids and capital projects

Open bids and the projects in this authority's capital plan, with costs. Bids come from COMMBUYS; projects come from the annual plan the authority files with the state.

Open bids

None on COMMBUYS as of Sep 27, 2026. Get the free weekly email to hear when one posts.

Proposed for fiscal 2027 (7 projects, $558,984)

State fiscal year: July 2026 to June 2027. Available formula funding for the year, per the plan: $184,719. Proposals can run well past that; some depend on special awards from the state.

ProjectDevelopmentTotal project cost
Electric Heater replacement
Heating, boilers & HVAC
Valley View$9,432
Replace 1 Boiler 667-2
Heating, boilers & HVAC · special award requested: $11,344
Valley View Annex$11,344
Additional Parking 667-1
Paving, walkways & site
Valley View$162,110
New Vinyl Fence
Paving, walkways & site
Valley View$9,831
Water Heater Replacement
Heating, boilers & HVAC
Weir River Apts$140,683
Replace Unit Entry Doors and Locksets - Valley View / Annex
Windows & doors
$149,845
667-1 Sidewalk and Railing Repairs - Valley View / Annex
Paving, walkways & site
$75,739

Proposed for fiscal 2028 (2 projects, $199,138)

State fiscal year: July 2027 to June 2028. Anticipated formula funding for the year, per the plan: $184,719. Proposals can run well past that; some depend on special awards from the state.

ProjectDevelopmentTotal project cost
New Pavilion
Other
Weir River Apts$147,542
Replace Kitchen Cabinets
Kitchens & baths
Valley View$51,596

Proposed for fiscal 2029 (2 projects, $173,181)

State fiscal year: July 2028 to June 2029. Anticipated formula funding for the year, per the plan: $184,719. Proposals can run well past that; some depend on special awards from the state.

ProjectDevelopmentTotal project cost
New Generator
Electrical & generators
Valley View$124,781
Paint Common Hallways - Annex
Interiors, flooring & painting
Valley View Annex$48,400

Further out: fiscal 2030–2031 (3 projects, $388,713)

The plan's “Years 4 and 5”: rough planning amounts, further out. State fiscal years: July 2029 to June 2031.

ProjectDevelopmentTotal project cost
Paint Common Hallways
Interiors, flooring & painting
Valley View$127,050
Handicap Door Openers
Windows & doors
Valley View$87,725
Re-Roofing Building #1 & 2
Roofing & gutters
Valley View$173,938

Active projects (13)

The plan's list of projects already under way: some in design or out to bid, some under construction or wrapping up. When one goes out to bid, the COMMBUYS title is sometimes just its FISH number.

ProjectDevelopmentTotal project cost
AIP: 667 Routine Turnovers
FISH 316105
$17,200
Vacant Turnover 667-1
FISH 316099
Valley View$9,375
Replace Light Pole Heads + 4 Poles
FISH 316100
Valley View$7,500
Parking Lot Rplcmt - Annex 667-2
FISH 316101
Valley View Annex$109,800
Siding Repairs
FISH 316103
Weir River Apts$9,775
Bldg 1 Bathrooms 667-1
FISH 316104
$69,000
Replace Community Hall Siding
FISH 316106
Valley View$61,200
Flooring Upgrades
FISH 316107
Valley View$9,375
Vacant Turnover- WEIR
FISH 316108
Weir River Apts$8,750
ARPA & FF Paving at 705-2
FISH 316076
161 West Street$390,858
Window Replacement 705-2
FISH 316086
161 West Street$187,626
Modernization of Vacant Unit Phase 1
FISH 316095
Valley View Annex$5,000
ARPA Targeted Award Fire Alarms -ER 667-1 & 67-2 Devices & 1 panel
FISH 316098
Weir River Apts$100,146

Costs are total project costs (design and construction) as listed in the plan, read automatically from the PDF. The plans schedule work by the state's fiscal year (July to June), which can differ from an authority's own. Proposed projects are not funded until the state approves them, and plans change: costs rise, projects slip or get split into phases. Check the plan itself before relying on a number.