Open bids and capital projects
Open bids and the projects in this authority's capital plan, with costs. Bids come from COMMBUYS; projects come from the annual plan the authority files with the state.
None on COMMBUYS as of Sep 27, 2026. Get the free weekly email to hear when one posts.
This authority's newest plan on the state portal uses the state's previous format. “Spending planned” lists the state fiscal years (July to June) with money scheduled for each project; fiscal 2026 and earlier have already ended. “—” means the plan shows no spending scheduled for it in those years.
| Project | Development | Total cost | Spending planned |
|---|---|---|---|
| Common area flooring replacement FISH 295062 · Interiors, flooring & painting | Roy Way 689-01 | $10,890 | 2026 |
| Rehab Bathrooms - Phase 2 FISH 295070 · Kitchens & baths | Saunders Circle 667-03 | $607,222 | — |
| Interior common area painting FISH 295075 · Interiors, flooring & painting | Pond View Lane 167-01 | $10,890 | 2026 |
| Kitchen Cabinet, Countertop Replacement and Flooring Finishes FISH 295082 · Kitchens & baths | Pondview Street 689-02 | $107,306 | — |
| Driveway repairs and seal coating FISH 295083 · Paving, walkways & site | Pond View Lane 167-01 | $9,999 | 2026 |
| ARPA FF: Bathroom renovations FISH 295086 · Kitchens & baths | Pondview Street 689-02 | $76,450 | 2026 |
| Roof Replacement FISH 295088 · Roofing & gutters | Pondview Lane 705-03 | $155,515 | — |
| Community Room Upgrade FISH 295089 · Interiors, flooring & painting | Saunders Circle 667-03 | $106,231 | 2026 |
| New common area flooring & repaint stairwells FISH 295090 · Interiors, flooring & painting | Saunders Circle 667-03 | $154,831 | 2026 |
| SUS-Bathroom Exhaust Fans FISH 295091 · Heating, boilers & HVAC | 667-01, 667-02, 667-03, 167-01, 689-01, 689-02 | $469,309 | 2026 |
| ARPA Targeted Award - Tewksbury FA Upgrade, FedPac and GFCI replacement FISH 295091 · Electrical & generators | 667-01, 667-02, 667-03, 167-01, 689-01, 689-02 | $707,581 | 2026 |
| Window Replacement (667-2) - Phase 2 FISH 295092 · Windows & doors | Carnation Drive 667-02 | $250,100 | 2026 |
| **EMG** Boiler Replacement FISH 295093 · Heating, boilers & HVAC | Pondview Lane 705-03 | $9,680 | — |
| ***EMG*** Sewer Main line repair/clog FISH 295095 · Water, sewer & plumbing | Saunders Circle 667-03 | $24,930 | — |
| Entry Door Replacement Dev-Wide FISH — · Windows & doors | Carnation Drive 667-01 | $223,850 | 2028 |
| New exterior doors 667-2 FISH — · Windows & doors | Carnation Drive 667-02 | $223,850 | 2029 |
Costs are total project costs (design and construction) as listed in the plan, read automatically from the PDF. The plans schedule work by the state's fiscal year (July to June), which can differ from an authority's own. Proposed projects are not funded until the state approves them, and plans change: costs rise, projects slip or get split into phases. Check the plan itself before relying on a number.