This authority's newest plan on the state portal uses the state's previous format. “Spending planned” lists the state fiscal years (July to June) with money scheduled for each project; fiscal 2026 and earlier have already ended. “—” means the plan shows no spending scheduled for it in those years. The plan also lists 1 project paid for entirely outside formula funding (special awards, grants or other sources, about $4,700 in all) in a separate table, not shown here.
| Project | Development | Total cost | Spending planned |
|---|---|---|---|
| 2008 FF Master CFA FISH 288020 · Other | Musketahquid Village 667-01 | $1,563 | — |
| Hood Fan Installation SUST Request FISH 288066 · Heating, boilers & HVAC | Musketahquid Village 667-01 | $293,635 | 2026 |
| ARPA FF: Fire Alarm Upgrade FISH 288071 · Fire alarm & sprinklers | Musketahquid Village 667-01 | $879,902 | 2026 |
| Feasibility study (redevelopment) scattered site 705s FISH 288073 · Studies & design | Great Lake Dr 705-1A | $73,603 | — |
| Fire Road Paving/705 Drainage Improvements FISH 288074 · Paving, walkways & site | 667-1, 705-4, 705-1A | $0 | — |
| Septic System replacement TARGETED LIST (DHCD ER) FISH 288075 · Water, sewer & plumbing | Fairbank Old Meadow Pine 705-04 | $290,000 | 2026–2027 |
| unit 10B reasonable accommodation FISH 288080 · Accessibility (ADA) | Musketahquid Village 667-01 | $12,434 | 2026 |
| Replace gate valves for water main FISH 288081 · Water, sewer & plumbing | Musketahquid Village 667-01 | $63,576 | 2026 |
| Lever door handles and keyed locksets FISH 288084 · Windows & doors | Musketahquid Village 667-01 | $29,040 | 2026–2027 |
| Security Cameras FISH 288085 · Security & access | Musketahquid Village 667-01 | $9,890 | 2026 |
| Moisture/Air Quality Study FISH — · Studies & design | Musketahquid Village 667-01 | $21,275 | — |
| Entry door unit overhangs FISH — · Windows & doors | Fairbank Old Meadow Pine 705-04 | $231,261 | 2027–2028 |
| New Sheds 705-4 FISH — · Other | Fairbank Old Meadow Pine 705-04 | $98,736 | 2030 |
Costs are total project costs (design and construction) as listed in the plan, read automatically from the PDF. The plans schedule work by the state's fiscal year (July to June), which can differ from an authority's own. Proposed projects are not funded until the state approves them, and plans change: costs rise, projects slip or get split into phases. Check the plan itself before relying on a number.