Plainbids · All housing authorities · Updated Sep 27, 2026

Stoneham Housing Authority

Open bids and capital projects

Open bids and the projects in this authority's capital plan, with costs. Bids come from COMMBUYS; projects come from the annual plan the authority files with the state.

Open bids

None on COMMBUYS as of Sep 27, 2026. Get the free weekly email to hear when one posts.

Projects in its capital plan (12, $4,598,354 total cost)

This authority's newest plan on the state portal uses the state's previous format. “Spending planned” lists the state fiscal years (July to June) with money scheduled for each project; fiscal 2026 and earlier have already ended. “—” means the plan shows no spending scheduled for it in those years.

ProjectDevelopmentTotal costSpending planned
Replace Roof
FISH 284108 · Roofing & gutters
Parker Chase 1 & 2$499,3752026
ARPA TARGETED: 667-2 & 3 ADA Unit Accessibility Project
FISH 284109 · Accessibility (ADA)
Parker Chase 1 667-02$1,137,0312026
Bathroom Rehab DEV-Wide
FISH 284110 · Kitchens & baths
Washington Elderly 667-01$729,8152026
Painting Fronts Calthea/Wash. St.
FISH 284113 · Interiors, flooring & painting
Calthea & Washington Street 200-01$11,6002026
Duncklee Bathrooms Phase 1
FISH 284114 · Kitchens & baths
Duncklee Avenue 667-04$717,0672026–2027
Emergency DCAMM Roof Replacement Comm. Rm.
FISH 284116 · Roofing & gutters
Duncklee Avenue 667-04$64,3402026
Calthea & Washington Street Front Entry Door Replacement
FISH — · Windows & doors
Calthea & Washington Street 200-01$161,1012027–2028
New bulkheads
FISH — · Other
Calthea & Washington Street 200-01$70,1332028
New Kitchens/painting / flooring Washington Ave Elderly
FISH — · Kitchens & baths
Washington Elderly 667-01$503,4122029–2030
New replacement windows office
FISH — · Windows & doors
Parker Chase 1 667-02$14,0062026
Duncklee Bathrooms Phase 2
FISH — · Kitchens & baths
Duncklee Avenue 667-04$608,2132026–2027
New wall mailboxes
FISH — · Security & access
Duncklee Avenue 667-04$82,2612026

Costs are total project costs (design and construction) as listed in the plan, read automatically from the PDF. The plans schedule work by the state's fiscal year (July to June), which can differ from an authority's own. Proposed projects are not funded until the state approves them, and plans change: costs rise, projects slip or get split into phases. Check the plan itself before relying on a number.

Get every housing authority bid, every Monday. Free.