Plainbids · All housing authorities · Updated Sep 27, 2026
Open bids and capital projects
Open bids and the projects in this authority's capital plan, with costs. Bids come from COMMBUYS; projects come from the annual plan the authority files with the state.
State fiscal year: July 2026 to June 2027. Available formula funding for the year, per the plan: $112,996. Proposals can run well past that; some depend on special awards from the state.
| Project | Development | Total project cost |
|---|---|---|
| Elevator Safety Compliance Upgrades 667-1 Elevators · special award requested: $31,625 | Maushope | $31,625 |
| Vacant Unit Turnover 667-1 Unit 12 Unit turnovers & renovations · special award requested: $28,136 | Maushope | $28,136 |
State fiscal year: July 2027 to June 2028. Anticipated formula funding for the year, per the plan: $112,996. Proposals can run well past that; some depend on special awards from the state.
| Project | Development | Total project cost |
|---|---|---|
| Community Patio Upgrades 667-1 Other | Maushope | $75,352 |
| Exterior Door Replacement Aunt Sukey's Way Windows & doors | Maushope | $42,634 |
State fiscal year: July 2028 to June 2029. Anticipated formula funding for the year, per the plan: $112,996. Proposals can run well past that; some depend on special awards from the state.
| Project | Development | Total project cost |
|---|---|---|
| Main Entrance Doors and Comm. Room Sliding Door Replacement 667-1 Windows & doors | Maushope | $68,365 |
| Building Envelope Upgrade 35A Court St. Siding, masonry & exterior | Pearl Street / Court Street | $158,495 |
The plan's “Years 4 and 5”: rough planning amounts, further out. State fiscal years: July 2029 to June 2031.
| Project | Development | Total project cost |
|---|---|---|
| Repair Concrete Stoop and Landing Other | Pearl Street / Court Street | $40,112 |
| Selective Plumbing Replacement Water, sewer & plumbing | Maushope | $121,340 |
| Sustainability Replace Toilets Other | Maushope | $92,577 |
| Relocate Bathroom Doors Windows & doors | Maushope | $51,782 |
| Demo & Replace Front Stoop Other | Pearl Street / Court Street | $84,125 |
| Selective ADA Unit Accessibility Updates Accessibility (ADA) | Maushope | $163,631 |
| Hallway Carpet Replacement Project Interiors, flooring & painting | Maushope | $27,770 |
| Hallway & Common Area Painting Project Interiors, flooring & painting | Maushope | $12,402 |
| ADA Automatic Door Opener Upgrade Windows & doors | Maushope | $32,216 |
| ADA Unit Conversion Unit #1 Court Street Accessibility (ADA) | Pearl Street / Court Street | $138,070 |
| Electric Range Replacement 667- 1 Electrical & generators | Maushope | $38,010 |
| Building Envelope Upgrades 667- 1 Siding, masonry & exterior | Maushope | $909,580 |
The plan's list of projects already under way: some in design or out to bid, some under construction or wrapping up. When one goes out to bid, the COMMBUYS title is sometimes just its FISH number.
| Project | Development | Total project cost |
|---|---|---|
| AIP: 667 Routine Turnovers FISH 242086 | $4,800 | |
| EMG Septic System Replacement 667-1 Maushope FISH 242089 | $50,000 | |
| ARPA FF: VU23 Vacant Unit Turnover FISH 242065 | Maushope | $12,895 |
| ARPA FF: ADA Accessible Showers & Bathroom Upgrades (2 Units) FISH 242071 | Maushope | $136,973 |
| ARPA Targeted Award: Provincetown Fire Alarm System Replacement FISH 242073 | Maushope | $262,538 |
| Elevator Safety Component Upgrade FISH 242078 | Maushope | $6,098 |
| Replace Door Buzzer System FISH 242080 | Maushope | $81,399 |
| Unit Flooring Replacement 667-1 FISH 242082 | Maushope | $14,735 |
| EMG Water Heater Replacement 705- 1 FISH 242083 | Pearl Street / Court Street | $12,110 |
| Rear Deck Replacement (Unit 2 40 Pearl St.) FISH 242085 | Pearl Street / Court Street | $102,715 |
| Building Envelope Upgrade (33 Court St.) FISH 242087 | Pearl Street / Court Street | $176,200 |
| EMG Blizzard Clean-Up/Tree Removal FISH 242088 | Maushope | $9,184 |
Costs are total project costs (design and construction) as listed in the plan, read automatically from the PDF. The plans schedule work by the state's fiscal year (July to June), which can differ from an authority's own. Proposed projects are not funded until the state approves them, and plans change: costs rise, projects slip or get split into phases. Check the plan itself before relying on a number.