Plainbids · All housing authorities · Updated Sep 27, 2026
Open bids and capital projects
Open bids and the projects in this authority's capital plan, with costs. Bids come from COMMBUYS; projects come from the annual plan the authority files with the state.
None on COMMBUYS as of Sep 27, 2026. Get the free weekly email to hear when one posts.
This authority's newest plan on the state portal uses the state's previous format. “Spending planned” lists the state fiscal years (July to June) with money scheduled for each project; fiscal 2026 and earlier have already ended. “—” means the plan shows no spending scheduled for it in those years.
| Project | Development | Total cost | Spending planned |
|---|---|---|---|
| FF: Bathroom Tub/Tile Surround PH II FISH 227028 · Kitchens & baths | Laurel Manor 667-01 | $9,000 | 2027 |
| ARPA FF: Update Laundry Room FISH 227041 · Other | Laurel Manor 667-01 | $63,302 | 2026–2027 |
| Paint Interior Of Community Hall FISH 227042 · Interiors, flooring & painting | Laurel Manor 667-01 | $9,500 | 2027 |
| Smoke Detector Upgrade FISH 227043 · Fire alarm & sprinklers | Laurel Manor 667-01 | $7,500 | 2027 |
| Remove Pine Trees FISH 227044 · Paving, walkways & site | Laurel Manor 667-01 | $9,500 | 2027 |
| Bathroom Tub/Tile Surround PH III FISH 227045 · Kitchens & baths | Laurel Manor 667-01 | $5,000 | 2027 |
| Replace Kitchen Counter Tops - PH I FISH 227046 · Kitchens & baths | Laurel Manor 667-01 | $9,800 | 2027 |
| Rehab at turnover FISH 227047 · Unit turnovers & renovations | Laurel Manor 667-01 | $9,960 | 2027 |
| Water Heater Breakers FISH — · Heating, boilers & HVAC | Laurel Manor 667-01 | $116,298 | 2028–2029 |
| Cedar Shake Siding FISH — · Siding, masonry & exterior | Laurel Manor 667-01 | $52,874 | 2027–2028 |
| Replace Asphalt parking areas FISH — · Paving, walkways & site | Laurel Manor 667-01 | $69,696 | 2026 |
Costs are total project costs (design and construction) as listed in the plan, read automatically from the PDF. The plans schedule work by the state's fiscal year (July to June), which can differ from an authority's own. Proposed projects are not funded until the state approves them, and plans change: costs rise, projects slip or get split into phases. Check the plan itself before relying on a number.