Open bids and capital projects
Open bids and the projects in this authority's capital plan, with costs. Bids come from COMMBUYS; projects come from the annual plan the authority files with the state.
None on COMMBUYS as of Sep 27, 2026. Get the free weekly email to hear when one posts.
The plan's list of projects already under way: some in design or out to bid, some under construction or wrapping up. When one goes out to bid, the COMMBUYS title is sometimes just its FISH number.
| Project | Development | Total project cost |
|---|---|---|
| Kitchen Modernization FISH — | Willowood 667-1 | $614,253 |
| Kitchen Modernization FISH — | Willowood 667-2 | $789,693 |
| AIP: 667 Routine Turnovers FISH 220089 | Nahatan Village 667-3 | $0 |
| AIP: 667 Routine Turnovers FISH 220089 | Nahatan Village 667-4 | $0 |
| AIP: 667 Routine Turnovers FISH 220089 | Willowood 667-1 | $0 |
| AIP: 667 Routine Turnovers FISH 220089 | Willowood 667-2 | $0 |
| Front Entry & Storm Doors Replacement. FISH — | Washington Heights | $432,424 |
| Fire Alarm System Upgrade FISH — | Nahatan Village 667-4 | $439,300 |
| Tree Trimming & Removal - Merged FISH 220102 | $15,805 | |
| Sust: Tree Replanting FISH 220101 | Nahatan Village 667-3 | $28,798 |
| AIP: 667 Routine Turnovers FISH 220089 | Willowood 667-1 | $47,600 |
| Roofing System Replacement - Phase 1 FISH 220079 | Washington Heights | $1,027,726 |
| SUST Exterior Lighting Improvements FISH 220080 | Nahatan Village 667-4 | $144,697 |
| Roofing System 667-3 Emergency FISH 220075 | Nahatan Village 667-3 | $275,523 |
| ARPA and EOHLC ER: Sewer Lines Replacement 667-1 & 2 Willowood FISH 220081 | Willowood 667-1 | $489,280 |
| Window and Exterior Aluminum Siding Replacement. FISH 220082 | Nahatan Village 667-3 | $350,000 |
| Refrigerator Replacement FISH 220083 | Willowood 667-1 | $116,449 |
| Retaining Wall Replacement FISH 220086 | Willowood 667-1 | $201,260 |
| Parking Lot Resurfacing/Relining FISH 220087 | Willowood 667-1 | $66,304 |
| Hot Water Heater Replacement FISH 220088 | Nahatan Village 667-4 | $348,766 |
| Electrical Upgrades FISH 220090 | $0 | |
| Add Additional Parking Spaces FISH 220091 | Washington Heights | $252,000 |
| Tub Surround Replacement - Phase 1 FISH 220092 | Willowood 667-1 | $170,320 |
| Smoking Detectors FISH 220094 | Willowood 667-1 | $8,625 |
| Reasonable Accommodation - Ramp Install - Building #19 FISH 220095 | Willowood 667-2 | $19,637 |
| Fire Alarm System Upgrade FISH 220100 | Nahatan Village 667-3 | $0 |
Costs are total project costs (design and construction) as listed in the plan, read automatically from the PDF. The plans schedule work by the state's fiscal year (July to June), which can differ from an authority's own. Proposed projects are not funded until the state approves them, and plans change: costs rise, projects slip or get split into phases. Check the plan itself before relying on a number.