Projects in its capital plan (21, $1,944,567 total cost)

This authority's newest plan on the state portal uses the state's previous format. “Spending planned” lists the state fiscal years (July to June) with money scheduled for each project; fiscal 2026 and earlier have already ended. “—” means the plan shows no spending scheduled for it in those years.

ProjectDevelopmentTotal costSpending planned
2008 FF Master CFA
FISH 215024 · Other
Colonial Village 667-01$2,400—
FF: Walkway Repave - Back of Dev
FISH 215063 · Paving, walkways & site
Colonial Village 667-01$37,485—
Temporary Driveway Repairs
FISH 215088 · Paving, walkways & site
Otis Street 705-2B$9,9002026
Concrete Patio
FISH 215097 · Other
Otis Street 705-2B$11,3852026
Roof Replacement
FISH 215102 · Roofing & gutters
Greenwood 705-1A$11,6892026
Vacant Unit Rehab
FISH 215103 · Unit turnovers & renovations
Emerson 705-1C$0—
New Bathroom Components
FISH 215111 · Kitchens & baths
Northgate 705-1B$10,4462026
Emergency Generator
FISH 215120 · Electrical & generators
Heritage Village 667-02$80,4632026
Roof Replacement
FISH 215121 · Roofing & gutters
Birch Hill 705-1D$10,780—
Vacant Unit Rehab
FISH 215122 · Unit turnovers & renovations
Birch Hill 705-1D$75,0002026
Replace Kitchens
FISH 215124 · Kitchens & baths
Crestwood Drive 705-2A$65,1352026
Fencing
FISH 215125 · Paving, walkways & site
Otis Street 705-2B$6,4312026
ARPA Targeted Award:167-01 Fire Alarm System Northboro
FISH 215126 · Fire alarm & sprinklers
Special Needs (DMH) 167-01$73,204—
ARPA Targeted: 667-1 Fed-Pacific panel replacement
FISH 215127 · Electrical & generators
Colonial Village 667-01$569,7592026
Deck Removal and Fire Escape Install
FISH 215128 · Siding, masonry & exterior
Special Needs (DMH) 167-01$58,3382026
Driveway Replacement.
FISH 215129 · Paving, walkways & site
Otis Street 705-2B$22,9742026
New Kitchens in (8) in Building 2-4
FISH — · Kitchens & baths
Colonial Village 667-01$224,6332030
Repave Parking Lot Phase 1
FISH — · Paving, walkways & site
Colonial Village 667-01$198,5612027
Repave Parking Lot Phase 2
FISH — · Paving, walkways & site
Colonial Village 667-01$165,4682029
New Entry Doors w/Sidelight
FISH — · Windows & doors
Heritage Village 667-02$237,9162026
*SUST* Bath Fans Heritage Village
FISH — · Heating, boilers & HVAC
Heritage Village 667-02$72,6002027

Costs are total project costs (design and construction) as listed in the plan, read automatically from the PDF. The plans schedule work by the state's fiscal year (July to June), which can differ from an authority's own. Proposed projects are not funded until the state approves them, and plans change: costs rise, projects slip or get split into phases. Check the plan itself before relying on a number.