Plainbids · All housing authorities · Updated Sep 27, 2026
Open bids and capital projects
Open bids and the projects in this authority's capital plan, with costs. Bids come from COMMBUYS; projects come from the annual plan the authority files with the state.
None on COMMBUYS as of Sep 27, 2026. Get the free weekly email to hear when one posts.
This plan's Active Projects table is empty, so some fiscal 2027 items below (emergency, ARPA-funded or routine turnover work) may already be under way.
State fiscal year: July 2026 to June 2027. Available formula funding for the year, per the plan: $296,350. Proposals can run well past that; some depend on special awards from the state.
| Project | Development | Total project cost |
|---|---|---|
| Replace front and Back doors at 667-1 Windows & doors | Fountain Drive | $498,218 |
| Common Area Hallway Painting at 667-4 Interiors, flooring & painting | O'Connor Heights | $45,375 |
| Window Replacement - CG Windows & doors | O'Connor Heights | $294,625 |
| Foulds Terrace Sidewalk / Curb / Apartment Stoop Upgrades / Repairs ? 667-3 Paving, walkways & site | Fould's Terrace | $204,256 |
| Bingham Way & OConnor Heights Tree Removal/Pruning-667-2 & 4 Paving, walkways & site | Bingham Way | $32,370 |
| Flagpole replacement 667 1-4 (four complexes) Other | Fountain Drive | $17,027 |
| Foulds Window Replacement- 667-3 Windows & doors | Fould's Terrace | $373,737 |
| AIP: 667 Routine Turnovers Unit turnovers & renovations | $32,800 | |
| Site Grading and Drainage Paving, walkways & site | Bingham Way | $174,275 |
| Tree Removal and Replacement Paving, walkways & site | Bingham Way | $43,346 |
| Asphalt Shingle Roof Replacement/Insulation Improvements -CG Roofing & gutters | O'Connor Heights | $215,618 |
| Vacancy Initiative Renovation Unit turnovers & renovations | Ashland Street | $322,102 |
| Concrete entry/stoop repairs Windows & doors | Fountain Drive | $402,402 |
| Window Replacement Windows & doors | Fountain Drive | $111,220 |
| Concrete Stair Repair/Replacement Siding, masonry & exterior | Bingham Way | $79,643 |
| Common Area Painting Interiors, flooring & painting | Bingham Way | $52,517 |
| CPC Community Generator. Electrical & generators | Fould's Terrace | $114,888 |
Costs are total project costs (design and construction) as listed in the plan, read automatically from the PDF. The plans schedule work by the state's fiscal year (July to June), which can differ from an authority's own. Proposed projects are not funded until the state approves them, and plans change: costs rise, projects slip or get split into phases. Check the plan itself before relying on a number.
Get every housing authority bid, every Monday. Free.