Open bids and the projects in this authority's capital plan, with costs. Bids come from COMMBUYS; projects come from the annual plan the authority files with the state.

Open bids

None on COMMBUYS as of Sep 27, 2026. Get the free weekly email to hear when one posts.

Further out: fiscal 2029–2030 (12 projects, $1,178,620)

The plan's “Years 4 and 5”: rough planning amounts, further out. State fiscal years: July 2028 to June 2030.

ProjectDevelopmentTotal project cost
Emergency Water Heater Replacement
Heating, boilers & HVAC
Chambers Street$4,150
Underground water line replacement
Other
Linden Street - 1$115,625
Fed Pacific panel replacements
Electrical & generators
Linden Street - 1$87,600
Exterior door replacement
Windows & doors
Linden Street - 1$21,901
Underground water line replacement
Other
Linden Street - 2$143,400
Exterior door replacement
Windows & doors
Linden Street - 2$52,938
window replacement
Windows & doors
Linden Street - 2$292,320
Fed Pacific panel replacements
Electrical & generators
Linden Street - 2$72,000
Linden St 667-2 Trim wrap and vinyl soffit
Siding, masonry & exterior
Linden Street - 2$59,384
Laundry Room Flooring Replacement- Dev wide
Interiors, flooring & painting
Chambers Street$53,270
Emergency Generator Replacement
Electrical & generators
Chambers Street$113,438
New pole lighting and Underground Conduit
Electrical & generators
Chambers Street$162,594

Costs are total project costs (design and construction) as listed in the plan, read automatically from the PDF. The plans schedule work by the state's fiscal year (July to June), which can differ from an authority's own. Proposed projects are not funded until the state approves them, and plans change: costs rise, projects slip or get split into phases. Check the plan itself before relying on a number.