Open bids and capital projects
Open bids and the projects in this authority's capital plan, with costs. Bids come from COMMBUYS; projects come from the annual plan the authority files with the state.
This authority's newest plan on the state portal uses the state's previous format. “Spending planned” lists the state fiscal years (July to June) with money scheduled for each project; fiscal 2026 and earlier have already ended. “—” means the plan shows no spending scheduled for it in those years.
| Project | Development | Total cost | Spending planned |
|---|---|---|---|
| 2008 FF Master CFA FISH 181061 · Other | J.F.K. Village 200-01 | $750 | — |
| Roll-in Showers and Bath Fans FISH 181113 · Heating, boilers & HVAC | Edgewood Avenue Elderly 667-02 | $1,036,654 | 2026 |
| Bathroom Upgrade FISH 181123 · Kitchens & baths | Woodland Street 167-01 | $143,694 | — |
| ARPA Targeted Award: Methuen Fed Pac Panel and Fire Safety Syst FISH 181132 · Electrical & generators | 667-01, 667-03, 667-05, 689-03 | $2,281,552 | 2026 |
| Roof Replacement FISH 181139 · Roofing & gutters | Edgewood Avenue Elderly 667-02 | $68,530 | — |
| ADA Shower Renovation FISH 181140 · Kitchens & baths | Lowell Blvd Community Residence 689-03 | $54,752 | — |
| Mold removal FISH 181146 · Other | Lowell Blvd 705-01 | $9,865 | — |
| CR Emergency Elevator Repairs FISH 181148 · Elevators | Congregate- Elderly 667-05 | $42,500 | 2026 |
| Master Meter Methuen HA FISH 181154 · Other | 667-01, 667-02 | $0 | — |
| Roof Replacement FISH 181154 · Roofing & gutters | 667-01, 667-02 | $470,000 | 2026–2027 |
| Fire Alarm System Replacement FISH 181155 · Fire alarm & sprinklers | Edgewood Avenue Elderly 667-02 | $98,258 | 2026–2027 |
| *CR Request- ADA Openers 36 Oakland Ave. FISH 181156 · Accessibility (ADA) | Oakland Avenue Elderly 667-01 | $9,691 | 2026 |
| 1 full kitchen and 2 Bathroom Renovations FISH 181157 · Kitchens & baths | Haverhill Street Community Residence 689-01 | $107,657 | 2026 |
| Reasonable Accommodation Walk in shower FISH 181158 · Kitchens & baths | Oakland Avenue Elderly 667-01 | $13,535 | — |
| Asphalt Repairs Oakland FISH 181159 · Paving, walkways & site | Oakland Avenue Elderly 667-01 | $9,993 | — |
| Vacant Unit -75 Edgewood Ave. #9 FISH 181162 · Unit turnovers & renovations | Edgewood Avenue Elderly 667-02 | $147,990 | 2026–2027 |
| ADA Automatic Door Reasonable Accommodation FISH 181163 · Windows & doors | Lowell Blvd 705-01 | $9,224 | 2026 |
| Reasonable Accommodation walkway FISH 181164 · Paving, walkways & site | Lowell Blvd 705-01 | $9,200 | 2026 |
| Emergency Heat/AC Replacement FISH 181165 · Heating, boilers & HVAC | Mystic St Family Housing & Riverview Condos 705-02 | $7,638 | — |
| Reasonable Accommodation Request: Walk In Shower FISH 181167 · Kitchens & baths | Oakland Avenue Elderly 667-01 | $9,484 | 2026 |
| Community Room Generator FISH 181174 · Electrical & generators | Mystic Street Elderly 667-04 | $127,382 | 2026–2027 |
| Elevator repair/replace FISH 181176 · Elevators | Congregate- Elderly 667-05 | $298,158 | 2026–2027 |
| Automatic Access Gate FISH 181177 · Other | Congregate- Elderly 667-05 | $61,103 | 2026 |
| Two Shower Rooms FISH 181178 · Kitchens & baths | Congregate- Elderly 667-05 | $90,721 | 2026–2027 |
| Parking lot paving and roadway repairs FISH 181179 · Paving, walkways & site | Lowell Blvd 689-02 | $357,000 | 2026–2027 |
| SUST: HW & Boiler replacement FISH 181181 · Heating, boilers & HVAC | Oakland Avenue Elderly 667-01 | $102,094 | 2026–2027 |
| SUST: HW & Boiler replacement FISH 181181 · Heating, boilers & HVAC | Oakland Avenue Elderly 667-01 | $255,804 | 2026–2027 |
| DCAMM AC Replacement Community RM FISH 181182 · Other | Mystic Street Elderly 667-04 | $30,250 | 2026–2027 |
| New Group Home Kitchen FISH — · Kitchens & baths | Woodland Street 167-01 | $106,325 | 2027 |
| Exterior Door Project, Multiple Sites FISH — · Windows & doors | 167-01; 667-4; 667-2; 667-5 | $269,074 | 2026 |
| Parking and walkways Dev-Wide FISH — · Paving, walkways & site | J.F.K. Village 200-01 | $527,997 | 2026 |
| New entryway and Door project FISH — · Windows & doors | Oakland Avenue Elderly 667-01 | $80,163 | 2026 |
| Install new Store front Door/Window and Fire Escape FISH — · Windows & doors | Mystic Street Elderly 667-03 | $258,543 | 2026 |
| 36.5 A and B total bath rehabs-ADA FISH — · Kitchens & baths | Oakland Ave Community Residence 689-3A | $153,398 | 2026 |
| Asphalt Roof Replacement FISH — · Roofing & gutters | Lowell Blvd 705-01 | $368,872 | 2026 |
Costs are total project costs (design and construction) as listed in the plan, read automatically from the PDF. The plans schedule work by the state's fiscal year (July to June), which can differ from an authority's own. Proposed projects are not funded until the state approves them, and plans change: costs rise, projects slip or get split into phases. Check the plan itself before relying on a number.