Plainbids · All housing authorities · Updated Sep 27, 2026
Open bids and capital projects
Open bids and the projects in this authority's capital plan, with costs. Bids come from COMMBUYS; projects come from the annual plan the authority files with the state.
None on COMMBUYS as of Sep 27, 2026. Get the free weekly email to hear when one posts.
State fiscal year: July 2026 to June 2027. Available formula funding for the year, per the plan: $128,592. Proposals can run well past that; some depend on special awards from the state.
| Project | Development | Total project cost |
|---|---|---|
| *sus* roof insulation Roofing & gutters · special award requested: $153,472 | Merri Village | $153,472 |
| hot water heater replacement Heating, boilers & HVAC · special award requested: $9,831 | Merri Village | $9,831 |
| concrete stair repair Siding, masonry & exterior · special award requested: $9,831 | Merri Village | $9,831 |
State fiscal year: July 2027 to June 2028. Anticipated formula funding for the year, per the plan: $128,592. Proposals can run well past that; some depend on special awards from the state.
| Project | Development | Total project cost |
|---|---|---|
| Building envelope Siding, masonry & exterior | Merri Village | $67,736 |
| tree removal Paving, walkways & site | Merri Village | $9,831 |
State fiscal year: July 2028 to June 2029. Anticipated formula funding for the year, per the plan: $128,592. Proposals can run well past that; some depend on special awards from the state.
| Project | Development | Total project cost |
|---|---|---|
| Bathroom Upgrades Phase 2 Kitchens & baths | Merri Village | $143,082 |
The plan's “Years 4 and 5”: rough planning amounts, further out. State fiscal years: July 2029 to June 2031.
| Project | Development | Total project cost |
|---|---|---|
| Kitchen Upgrades (phase 1) Kitchens & baths | Merri Village | $266,878 |
| Roadway paving Phase 1 Paving, walkways & site | Merri Village | $79,200 |
The plan's list of projects already under way: some in design or out to bid, some under construction or wrapping up. When one goes out to bid, the COMMBUYS title is sometimes just its FISH number.
| Project | Development | Total project cost |
|---|---|---|
| ARPA FF: Door Replacement Phase 2 FISH 180039 | Merri Village | $146,336 |
| AIP: 667 Routine Turnovers FISH 180051 | $9,700 | |
| Kitchen Remodel FISH 180030 | Lincoln Street / Green Street | $20,800 |
| *SUS* Install bathroom exhaust fans FISH 180042 | Merri Village | $145,996 |
| Bathroom Upgrades Phase 1 FISH 180043 | Merri Village | $186,082 |
| Rear Deck Replacement FISH 180047 | Lincoln Street / Green Street | $74,396 |
| Vacant unit upgrades FISH 180048 | Lincoln Street / Green Street | $13,890 |
| Replace Mailboxes FISH 180049 | Merri Village | $7,364 |
| Replacement of Kitchen Hood Fans SUST FISH 180052 | Merri Village | $123,500 |
Costs are total project costs (design and construction) as listed in the plan, read automatically from the PDF. The plans schedule work by the state's fiscal year (July to June), which can differ from an authority's own. Proposed projects are not funded until the state approves them, and plans change: costs rise, projects slip or get split into phases. Check the plan itself before relying on a number.
Get every housing authority bid, every Monday. Free.