Open bids and capital projects

Open bids and the projects in this authority's capital plan, with costs. Bids come from COMMBUYS; projects come from the annual plan the authority files with the state.

Open bids

None on COMMBUYS as of Sep 27, 2026. Get the free weekly email to hear when one posts.

Proposed for fiscal 2027 (2 projects, $712,964)

State fiscal year: July 2026 to June 2027. Available formula funding for the year, per the plan: $193,724. Proposals can run well past that; some depend on special awards from the state.

ProjectDevelopmentTotal project cost
689 Siding Replacement - Additional Cost ? Add To CapHub #176089
Siding, masonry & exterior
Foster Court$17,214
Redevelopment of Walking Court FISH 176085 - FY 27 Additional FF to Phase 2
Other
Walkling Court$695,750

Proposed for fiscal 2028 (1 project, $151,250)

State fiscal year: July 2027 to June 2028. Anticipated formula funding for the year, per the plan: $193,724. Proposals can run well past that; some depend on special awards from the state.

ProjectDevelopmentTotal project cost
Redevelopment of Walking Court FISH 176085 - FY 28 Additional FF to Phase 2
Other
Walkling Court$151,250

Proposed for fiscal 2029 (1 project, $151,250)

State fiscal year: July 2028 to June 2029. Anticipated formula funding for the year, per the plan: $193,724. Proposals can run well past that; some depend on special awards from the state.

ProjectDevelopmentTotal project cost
Redevelopment of Walking Court FISH 176085 - FY 29 Additional FF to Phase 2
Other
Walkling Court$151,250

Further out: fiscal 2030–2031 (2 projects, $302,500)

The plan's “Years 4 and 5”: rough planning amounts, further out. State fiscal years: July 2029 to June 2031.

ProjectDevelopmentTotal project cost
Redevelopment of Walking Court FISH 176085 - FY 30 Additional FF to Phase 2
Other
Walkling Court$151,250
Redevelopment of Walking Court FISH 176085 - FY 31 Additional FF to Phase 2
Other
Walkling Court$151,250

Active projects (6)

The plan's list of projects already under way: some in design or out to bid, some under construction or wrapping up. When one goes out to bid, the COMMBUYS title is sometimes just its FISH number.

ProjectDevelopmentTotal project cost
AIP: 667 Routine Turnovers
FISH 176098
$28,800
Public Housing Innovations: Medford Planning Grant 667-1
FISH 176085
Walkling Court$15,350,000
ARPA FF: Site- Parking Lot Resurfacing 689-1
FISH 176088
Foster Court$118,870
Selective Siding Replacement
FISH 176089
Foster Court$13,560
Redevelopment of Walking Court FISH 176085 - Phase 2
FISH 176096
Walkling Court$363,000
Wood Stockade Fence Replacement
FISH 176097
Walkling Court$0

Costs are total project costs (design and construction) as listed in the plan, read automatically from the PDF. The plans schedule work by the state's fiscal year (July to June), which can differ from an authority's own. Proposed projects are not funded until the state approves them, and plans change: costs rise, projects slip or get split into phases. Check the plan itself before relying on a number.