Open bids and the projects in this authority's capital plan, with costs. Bids come from COMMBUYS; projects come from the annual plan the authority files with the state.
State fiscal year: July 2026 to June 2027. Available formula funding for the year, per the plan: $79,654. Proposals can run well past that; some depend on special awards from the state.
| Project | Development | Total project cost |
|---|---|---|
| Laundry Room Upgrades Other | Frank J. Homeyer Village | $63,652 |
| Replace Gas Boilers with ASHP 705-1 Heating, boilers & HVAC · special award requested: $375,106 | Breezy Acres - Breezy Way | $300,085 |
| EMG Mold Remediation 667-1 Unit 10 Other | Frank J. Homeyer Village | $11,357 |
| Vacant Unit Turnover #13 and #16 667-1 Unit turnovers & renovations · special award requested: $11,344 | Frank J. Homeyer Village | $11,344 |
| EMG Fire Alarm Panel Replacement 667-1 Fire alarm & sprinklers · special award requested: $18,149 | Frank J. Homeyer Village | $18,150 |
| 667 Stand Alone Community Building Other · special award requested: $496,362 | Frank J. Homeyer Village | $496,362 |
| Units 13B + 15A Mold Remediation Other | Frank J. Homeyer Village | $9,075 |
State fiscal year: July 2027 to June 2028. Anticipated formula funding for the year, per the plan: $79,654. Proposals can run well past that; some depend on special awards from the state.
| Project | Development | Total project cost |
|---|---|---|
| Tree Trimming and Removal Paving, walkways & site | Frank J. Homeyer Village | $9,680 |
State fiscal year: July 2028 to June 2029. Anticipated formula funding for the year, per the plan: $79,654. Proposals can run well past that; some depend on special awards from the state.
| Project | Development | Total project cost |
|---|---|---|
| Parking Lot & Walkway Replacement 667-1 Paving, walkways & site | Frank J. Homeyer Village | $329,155 |
The plan's “Years 4 and 5”: rough planning amounts, further out. State fiscal years: July 2029 to June 2031.
| Project | Development | Total project cost |
|---|---|---|
| Fire Sprinkler System 667-1 Fire alarm & sprinklers | Frank J. Homeyer Village | $564,465 |
| Fire/Emergency Access Road 667- 1 Other | Frank J. Homeyer Village | $182,184 |
The plan's list of projects already under way: some in design or out to bid, some under construction or wrapping up. When one goes out to bid, the COMMBUYS title is sometimes just its FISH number.
| Project | Development | Total project cost |
|---|---|---|
| ARPA FF: Sidewalk & Catch Basin FISH 172064 | Breezy Acres - Breezy Way | $63,990 |
| AIP: 667 Routine Turnovers FISH 172077 | $9,988 | |
| Roofing, Windows and Siding FISH 172058 | Frank J. Homeyer Village | $917,175 |
| Septic System Replacement FISH 172062 | Frank J. Homeyer Village | $8,000 |
| Dumpster Enclosure Upgrades FISH 172071 | Frank J. Homeyer Village | $56,990 |
| EMG Heat and Hot Water Mixing Valve Replacement 705-1 FISH 172072 | Breezy Acres - Breezy Way | $3,567 |
| Vacant Unit Rehab 667-1 Unit #9 FISH 172076 | Frank J. Homeyer Village | $72,760 |
| Bathroom Ventilation Upgrades 667- 1/705-1 FISH 172081 | Frank J. Homeyer Village | $12,485 |
| Mold Remediation Unit #21 FISH 172085 | Frank J. Homeyer Village | $8,488 |
| Circulator Pump Replacement 667-1 FISH 172086 | Frank J. Homeyer Village | $7,124 |
| Mold Remediation & Restoration 705-1 15A FISH 172087 | Breezy Acres - Breezy Way | $10,115 |
Costs are total project costs (design and construction) as listed in the plan, read automatically from the PDF. The plans schedule work by the state's fiscal year (July to June), which can differ from an authority's own. Proposed projects are not funded until the state approves them, and plans change: costs rise, projects slip or get split into phases. Check the plan itself before relying on a number.