Plainbids · All housing authorities · Updated Sep 27, 2026
Open bids and capital projects
Open bids and the projects in this authority's capital plan, with costs. Bids come from COMMBUYS; projects come from the annual plan the authority files with the state.
This authority's newest plan on the state portal uses the state's previous format. “Spending planned” lists the state fiscal years (July to June) with money scheduled for each project; fiscal 2026 and earlier have already ended. “—” means the plan shows no spending scheduled for it in those years.
| Project | Development | Total cost | Spending planned |
|---|---|---|---|
| ADA Updates - Hearing Impaired Tenant’s Unit FISH 149067 · Accessibility (ADA) | Stadium Courts 200-01 | $2,000 | 2026 |
| ADA - Reasonable Accommodation - TBD FISH 149070 · Accessibility (ADA) | Stadium Courts 200-01 | $16,697 | 2026 |
| Replace Roof - Administration Building FISH 149071 · Roofing & gutters | 200-2 and 667-1 | $461,199 | 2026 |
| High voltage eqipment replacement FISH 149072 · Other | Stadium Courts 200-01 | $3,296,817 | 2026–2027 |
| Unit Rehab - Replace Carpets - OR FISH 149073 · Interiors, flooring & painting | Brunswick House 667-01 | $375,518 | — |
| Metal bulkhead hatches FISH 149077 · Other | Stadium Courts 200-01 | $23,100 | 2026 |
| Parking Lot Reconfiguration and Gate Installation FISH 149078 · Paving, walkways & site | Brunswick House 667-01 | $241,914 | 2027 |
| Walkway Repairs FISH 149081 · Paving, walkways & site | Brunswick House 667-01 | $10,436 | 2026 |
| Interior Gas Line Replacement FISH 149082 · Interiors, flooring & painting | Hancock Courts 200-02 | $82,514 | — |
| DER Feasibility Study FISH 149083 · Studies & design | Stadium Courts 200-01 | $1,696,718 | 2027 |
| ADA (Unit) Kitchen Updates-1 FISH 149086 · Kitchens & baths | Brunswick House 667-01 | $33,293 | 2026–2027 |
| Stadium Courts-HC DER Feasibility (Add FF) for FISH 149083 FISH — · Studies & design | Stadium Courts 200-01 | $741,125 | 2026–2027 |
Costs are total project costs (design and construction) as listed in the plan, read automatically from the PDF. The plans schedule work by the state's fiscal year (July to June), which can differ from an authority's own. Proposed projects are not funded until the state approves them, and plans change: costs rise, projects slip or get split into phases. Check the plan itself before relying on a number.