Proposed for fiscal 2027 (3 projects, $491,562)

State fiscal year: July 2026 to June 2027. Available formula funding for the year, per the plan: $126,714. Proposals can run well past that; some depend on special awards from the state.

ProjectDevelopmentTotal project cost
GCT Front Door Replacement, 20 Doors- (PHASE 2)
Windows & doors
Golden Court Apts$181,500
VUI, 103 Burkeway
Other · special award requested: $158,812
Burkeway Apts.$158,812
VUI, 105 Burkeway
Other · special award requested: $88,982
Burkeway Apts.$151,250

Proposed for fiscal 2028 (1 project, $181,500)

State fiscal year: July 2027 to June 2028. Anticipated formula funding for the year, per the plan: $126,714. Proposals can run well past that; some depend on special awards from the state.

ProjectDevelopmentTotal project cost
GCT Front Door Replacement, Final 20 Doors- (PHASE 3)
Windows & doors
Golden Court Apts$181,500

Proposed for fiscal 2029 (4 projects, $113,073)

State fiscal year: July 2028 to June 2029. Anticipated formula funding for the year, per the plan: $126,714. Proposals can run well past that; some depend on special awards from the state.

ProjectDevelopmentTotal project cost
Replace Fence
Paving, walkways & site
Burkeway Apts.$19,375
Walkway resurfacing
Paving, walkways & site
Golden Court Apts$66,698
Install Permanant Exterior Seating
Siding, masonry & exterior
Golden Court Apts$11,875
Tree Pruning
Paving, walkways & site
Golden Court Apts$15,125

Further out: fiscal 2030–2031 (3 projects, $245,797)

The plan's “Years 4 and 5”: rough planning amounts, further out. State fiscal years: July 2029 to June 2031.

ProjectDevelopmentTotal project cost
Kitchen countertop replacement
Kitchens & baths
Golden Court Apts$25,536
Repave Driveway and Parking
Paving, walkways & site
Golden Court Apts$137,073
Replace Asphalt PH 1
Paving, walkways & site
Golden Court Apts$83,188

Active projects (9)

The plan's list of projects already under way: some in design or out to bid, some under construction or wrapping up. When one goes out to bid, the COMMBUYS title is sometimes just its FISH number.

ProjectDevelopmentTotal project cost
ARPA FF: GCT - Chimney Repairs
FISH 117084
Golden Court Apts$30,522
ARPA FF: 107 Burkeway Unit Turnover
FISH 117086
Burkeway Apts.$142,648
AIP: 667 Routine Turnovers
FISH 117100
$8,000
GCT - Rear Doors Replacement (PHASE 1 & PHASE 2)
FISH 117092
Golden Court Apts$369,685
VUI
FISH 117095
Golden Court Apts$80,868
VUI Golden Court #28 and #30
FISH 117096
Golden Court Apts$21,263
VUI Burke Way #104
FISH 117098
Burkeway Apts.$163,000
Fire Avert Safety Device
FISH 117101
Golden Court Apts$8,125
Select Tree & Debris Removal
FISH 117102
Golden Court Apts$12,494

Costs are total project costs (design and construction) as listed in the plan, read automatically from the PDF. The plans schedule work by the state's fiscal year (July to June), which can differ from an authority's own. Proposed projects are not funded until the state approves them, and plans change: costs rise, projects slip or get split into phases. Check the plan itself before relying on a number.