Plainbids · All housing authorities · Updated Sep 27, 2026
Open bids and capital projects
Open bids and the projects in this authority's capital plan, with costs. Bids come from COMMBUYS; projects come from the annual plan the authority files with the state.
This authority's newest plan on the state portal uses the state's previous format. “Spending planned” lists the state fiscal years (July to June) with money scheduled for each project; fiscal 2026 and earlier have already ended. “—” means the plan shows no spending scheduled for it in those years.
| Project | Development | Total cost | Spending planned |
|---|---|---|---|
| 2008 FF Master CFA FISH 114007 · Other | Petapwag Place | $750 | — |
| FF: Roof vent repairs FISH 114023 · Roofing & gutters | Petapawag Place 667-01 | $2,000 | — |
| FF: Asphalt walk Paving/ADA Ramp FISH 114032 · Paving, walkways & site | Petapawag Place 667-01 | $5,000 | 2027 |
| FF: Fence Project for Childrens Safety FISH 114033 · Paving, walkways & site | Petapawag Place 667-01 | $10,249 | 2027 |
| Front Porch Modification for Egress FISH 114035 · Siding, masonry & exterior | Petapawag Place 667-01 | $10,200 | 2027 |
| ARPA Targeted Award: Groton Fire Alarm FISH 114038 · Fire alarm & sprinklers | Petapawag Place 667-01 | $282,838 | — |
| Vacant Unit: Force Acct FISH 114040 · Unit turnovers & renovations | Petapawag Place 667-01 | $31,519 | — |
| Sidewalk repairs FISH 114042 · Paving, walkways & site | Petapawag Place 667-01 | $5,294 | 2027 |
| Automatic Doors 667-1 FISH — · Windows & doors | Petapawag Place 667-01 | $29,272 | 2026 |
| Bathroom Exhaust/Hallway Make up Air System FISH — · Heating, boilers & HVAC | Petapawag Place 667-01 | $88,726 | 2026 |
| *SUST* Petapawag ASHP install FISH — · Heating, boilers & HVAC | Petapawag Place 667-01 | $514,250 | 2027–2028 |
| Corridor Carpet Replacement FISH — · Interiors, flooring & painting | Petapawag Place 667-01 | $69,878 | 2028–2029 |
| Installation of New Rear Walkways from Building FISH — · Paving, walkways & site | Petapawag Place 667-01 | $59,669 | 2029–2030 |
Costs are total project costs (design and construction) as listed in the plan, read automatically from the PDF. The plans schedule work by the state's fiscal year (July to June), which can differ from an authority's own. Proposed projects are not funded until the state approves them, and plans change: costs rise, projects slip or get split into phases. Check the plan itself before relying on a number.
Get every housing authority bid, every Monday. Free.