Plainbids · All housing authorities · Updated Sep 27, 2026

Falmouth Housing Authority

Open bids and capital projects

Open bids and the projects in this authority's capital plan, with costs. Bids come from COMMBUYS; projects come from the annual plan the authority files with the state.

Open bids

None on COMMBUYS as of Sep 27, 2026. Get the free weekly email to hear when one posts.

Proposed for fiscal 2027 (3 projects, $577,585)

State fiscal year: July 2026 to June 2027. Available formula funding for the year, per the plan: $218,177. Proposals can run well past that; some depend on special awards from the state.

ProjectDevelopmentTotal project cost
Earmark Funding: Window Replacement 667-1
Windows & doors
Mayflower$414,009
Fire Sprinkler System Compliance Upgrade - Bayberry House
Fire alarm & sprinklers
Bayberry House$11,410
Vacant Unit Turnover 42 Jamie Ln
Unit turnovers & renovations · special award requested: $152,166
42 Jamie Lane$152,166

Proposed for fiscal 2028 (3 projects, $205,117)

State fiscal year: July 2027 to June 2028. Anticipated formula funding for the year, per the plan: $218,177. Proposals can run well past that; some depend on special awards from the state.

ProjectDevelopmentTotal project cost
Flooring Replacement (Bayberry)
Interiors, flooring & painting
Bayberry House$101,820
2nd Floor Bathroom Renovation - Bayberry
Kitchens & baths
Bayberry House$88,582
Handicap Accessible Ramp Reasonable Accommodation 38 Marshall Dr.
Accessibility (ADA)
38 Marshall Drive$14,715

Proposed for fiscal 2029 (1 project, $248,253)

State fiscal year: July 2028 to June 2029. Anticipated formula funding for the year, per the plan: $218,177. Proposals can run well past that; some depend on special awards from the state.

ProjectDevelopmentTotal project cost
Siding, Windows, & Door Replacement 28 Milton
Windows & doors
28 Milton Street$248,253

Further out: fiscal 2030–2031 (3 projects, $1,613,205)

The plan's “Years 4 and 5”: rough planning amounts, further out. State fiscal years: July 2029 to June 2031.

ProjectDevelopmentTotal project cost
Replace wood shingles
Other
Salt Sea$761,668
Building Envelope Upgrade 667-1
Siding, masonry & exterior
Mayflower$805,285
Window & Door Replacement 42 Jamie Ln.
Windows & doors
42 Jamie Lane$46,252

Active projects (25)

The plan's list of projects already under way: some in design or out to bid, some under construction or wrapping up. When one goes out to bid, the COMMBUYS title is sometimes just its FISH number.

ProjectDevelopmentTotal project cost
VUI 189 Old Barnstable Rd.
FISH 096103
$335,702
AIP: 667 Routine Turnovers
FISH 096112
$10,800
Screen doors, bulkhead and window screens
FISH 096072
Bayberry House$5,000
ARPA TAR & FF 38 Marshall Drive- Vacant Unit Turnover
FISH 096086
$186,842
Roof Replacement Project
FISH 096090
$30,960
VUI 130 Edgewater West
FISH 096091
$238,142
Kitchen Rehab Project
FISH 096092
$125,975
VUI 20 Madeline Rd
FISH 096096
$201,491
Windows & Painting at Salt Sea
FISH 096099
Salt Sea$592,637
ARPA FF Basement/Boiler Room Stairwell Retaining Wall Repair
FISH 096100
Mayflower$67,742
VUI 44 Carolyn Ln
FISH 096101
$213,620
Site Drainage & Crawlspace Waterproofing
FISH 096104
Mayflower$636,225
Tree Trimming & Removal 705/667-1
FISH 096105
Mayflower$21,324
SUST Replace Gas Ranges with Electric Ranges 667-1
FISH 096106
Mayflower$137,356
Additional Parking Spaces
FISH 096107
Mayflower$9,900
Replace Gas Ranges with Electric Ranges 667-2
FISH 096108
Salt Sea$16,994
Roof Replacement Project
FISH 096109
$22,850
Vacant Unit Rehab Unit 2A 667-1
FISH 096111
Mayflower$49,155
ARPA FF and SUS Bathroom Exhaust Fans 667-1/667-2
FISH 096113
Mayflower$222,898
Storm Drainage & Basement Waterproofing 705-A
FISH 096114
$51,000
Vacant Unit Turnover 123 Maravista Ave. - task force
FISH 096115
$111,472
Family Housing Smoke & Carbon Monoxide Detector Updates
FISH 096117
$51,000
Building Ventilation Upgrades & Indoor Humidity Control 667-1
FISH 096118
Mayflower$10,000
EMG Boiler Repair 667-2 BLDG. D
FISH 096119
Salt Sea$0
Vacant Unit Turnover 28 Milton St.
FISH 096120
$0

Costs are total project costs (design and construction) as listed in the plan, read automatically from the PDF. The plans schedule work by the state's fiscal year (July to June), which can differ from an authority's own. Proposed projects are not funded until the state approves them, and plans change: costs rise, projects slip or get split into phases. Check the plan itself before relying on a number.

Get every housing authority bid, every Monday. Free.