Plainbids · All housing authorities · Updated Sep 27, 2026
Open bids and capital projects
Open bids and the projects in this authority's capital plan, with costs. Bids come from COMMBUYS; projects come from the annual plan the authority files with the state.
This authority's newest plan on the state portal uses the state's previous format. “Spending planned” lists the state fiscal years (July to June) with money scheduled for each project; fiscal 2026 and earlier have already ended. “—” means the plan shows no spending scheduled for it in those years.
| Project | Development | Total cost | Spending planned |
|---|---|---|---|
| FF: Kitchen Cabinet and Countertop Replacement - DMH FISH 095133 · Kitchens & baths | Stanley Ray Streets 167-01 | $63,920 | 2026 |
| FF: Vacancy Unit - Reduction - Initiative - 667-03 FISH 095146 · Unit turnovers & renovations | Bishop Joseph Eid 667-03 | $10,800 | — |
| FF: Replace Failing Fencing - 689-01 FISH 095148 · Paving, walkways & site | Staffed Apts 689-01 | $16,500 | 2027 |
| FF: Walkways & Patio Repairs 689-04 FISH 095149 · Paving, walkways & site | Bullock St/Oak Grove Ave 689-04 | $20,000 | — |
| FF: Replace Failing Fencing - 689-04 FISH 095150 · Paving, walkways & site | Bullock St/Oak Grove Ave 689-04 | $10,000 | — |
| FF: Bathtub/Shower Replacement FISH 095151 · Kitchens & baths | Staffed Apts 689-01 | $27,500 | 2026–2027 |
| FF: Bathroom Plumbing Fixture Replacement FISH 095152 · Water, sewer & plumbing | Bates/Orswell 689-03 | $34,000 | 2026–2027 |
| FF: Underground Elec phase 3 FISH 095155 · Other | Maple Gardens 200-02 | $256,827 | 2026 |
| Replace Roof - DDS FISH 095165 · Roofing & gutters | Staffed Apts 689-01 | $68,286 | 2026 |
| Deck Replacement - DMH FISH 095170 · Siding, masonry & exterior | Stanley Ray Streets 167-01 | $37,565 | 2026 |
| Walkways & Fencing Replacement FISH 095173 · Paving, walkways & site | Bullock St/Oak Grove Ave 689-04 | $36,152 | 2026 |
| Gateway Award, ARPA Targeted - Maple Gardens Comprehensive Project FISH 095177 · Other | Maple Gardens 200-02 | $12,245,236 | 2026–2027 |
| Interior Flooring, Trim & ADA Improvements - Stanley Ray St FISH 095178 · Siding, masonry & exterior | Stanley Ray Streets 167-01 | $16,695 | 2026 |
| Interior Flooring, Trim & ADA Improvements - Staffed Apts FISH 095179 · Siding, masonry & exterior | Staffed Apts 689-01 | $315,423 | 2026 |
| ARPA Targeted- Fall River Fed Pac Panel and Fire Alarm Syst FISH 095180 · Fire alarm & sprinklers | 167-01, 200-02, 667-03, 689-01, 689-02, 689-03 | $862,957 | 2026 |
| ARPA FF: Security Camera Installation FISH 095185 · Security & access | Maple Gardens 200-02 | $257,700 | 2026–2027 |
| Replacing 689 at 229 Highland Ave FISH 095186 · Other | Highland Avenue 689-02 | $437,500 | — |
| DMH - Kitchen Updates FISH 095187 · Kitchens & baths | Stanley Ray Streets 167-01 | $18,082 | 2026 |
| Replace Fire Pump - DHCD ER Request FISH 095188 · Fire alarm & sprinklers | Bishop Joseph Eid 667-03 | $15,750 | 2026 |
| Install New 2nd Elevator - Bishop Eid FISH 095189 · Elevators | Bishop Joseph Eid 667-03 | $2,170,099 | 2027–2028 |
| Kitchen Stove/Oven Replacement Bishop EID FISH 095190 · Kitchens & baths | Bishop Joseph Eid 667-03 | $285,858 | 2026–2027 |
| Replace Original Mechanical AC System FISH 095191 · Heating, boilers & HVAC | Staffed Apts 689-01 | $18,299 | 2026 |
| Replace Failing Gas Lines - Phase 2024 FISH 095192 · Other | Maple Gardens 200-02 | $336,301 | 2026 |
| Security Camera Sys Upgrade - Bishop Eid FISH 095193 · Security & access | Bishop Joseph Eid 667-03 | $37,056 | 2026–2027 |
| Basement Foundation Improvements – Possible Resiliency/Funds FISH 095194 · Paving, walkways & site | Maple Gardens 200-02 | $408,100 | 2026–2027 |
| Fire Alarm Upgrade-Improvements - DHCD ER Request FISH 095196 · Fire alarm & sprinklers | Highland Avenue 689-02 | $4,400 | 2026 |
| Corkey Row 68-70 Boiler Replacement FISH 095197 · Heating, boilers & HVAC | Corky Row 705-02 | $680,625 | 2026–2027 |
| Smoke / CO Detector Modernization FISH 095198 · Fire alarm & sprinklers | Corky Row 705-02 | $37,813 | 2026–2027 |
| Flooring , Trim and ADA Improvements - Elmer / Corbett FISH 095199 · Siding, masonry & exterior | Staffed Apts 689-01 | $275,467 | 2026–2027 |
| Maple Gardens Kitchens and Baths Upgrades-Phase 1 FISH — · Kitchens & baths | Maple Gardens 200-02 | $831,875 | 2027–2029 |
Costs are total project costs (design and construction) as listed in the plan, read automatically from the PDF. The plans schedule work by the state's fiscal year (July to June), which can differ from an authority's own. Proposed projects are not funded until the state approves them, and plans change: costs rise, projects slip or get split into phases. Check the plan itself before relying on a number.
Get every housing authority bid, every Monday. Free.