The plan's list of projects already under way: some in design or out to bid, some under construction or wrapping up. When one goes out to bid, the COMMBUYS title is sometimes just its FISH number.
| Project | Development | Total project cost |
|---|---|---|
| Selective sidewalk repairs / replacement FISH 079124 | Perron Lane Family Housing | $12,471 |
| Replace Front Stairs FISH 079120 | Scattered Site-- 92 Varnum Avenue | $13,612 |
| Replace exterior Front and side Stairs at 705-D & 705-C7 FISH 079121 | Scattered Site- 125 Sladen | $41,640 |
| Brush Cleanup FISH 079122 | Perron Lane Family Housing | $11,344 |
| Tree Removal FISH 079123 | 901 Mammoth | $11,344 |
| Replace foundation insulation and barrier FISH 079125 | Perron Lane Family Housing | $12,100 |
| New Exterior Doors DEV-Wide FISH — | 113 Parker Avenue | $119,639 |
| Kitchen Renovations FISH — | Perron Lane Special Needs | $78,760 |
| Install New flooring at Congregate floor FISH — | 901 Mammoth | $26,408 |
| EMG Electric Service Panel Replacement FISH 079126 | Scattered Site- 45 Bolton Ave | $10,588 |
| AIP: 667 Routine Turnovers FISH 079111 | $10,600 | |
| ARPA Targeted Award - Dracut - 667- 2C Fire Alarm System, Zoned, Complete FISH 079103 | 113 Parker Avenue | $124,680 |
| VU24 Unit rehab 27 Perron Lane FISH 079110 | Perron Lane Family Housing | $130,788 |
| Perron Ln Roof Replacement Phase 3 FISH 079113 | Perron Lane Family Housing | $128,949 |
| Kitchen and Bathroom renovation FISH 079114 | Scattered Site- 45 Bolton Ave | $105,114 |
| RA - Install ADA Shower FISH 079115 | Scattered Site- 67 Tanglewood Dr | $7,568 |
| RA - Exterior Ramp Installation FISH 079116 | Scattered Site- 67 Tanglewood Dr | $10,972 |
| EMG Boiler replacement FISH 079117 | Scattered Site- 47 and 49 Hampson St | $10,450 |
| EMG Tree Removal FISH 079118 | Scattered Site- 45 Bolton Ave | $6,600 |
| Targeted Generator Award Project FISH 079119 | 901 Mammoth | $46,625 |
Costs are total project costs (design and construction) as listed in the plan, read automatically from the PDF. The plans schedule work by the state's fiscal year (July to June), which can differ from an authority's own. Proposed projects are not funded until the state approves them, and plans change: costs rise, projects slip or get split into phases. Check the plan itself before relying on a number.