Plainbids · All housing authorities · Updated Sep 27, 2026

Dennis Housing Authority

Open bids and capital projects

Open bids and the projects in this authority's capital plan, with costs. Bids come from COMMBUYS; projects come from the annual plan the authority files with the state.

Open bids

None on COMMBUYS as of Sep 27, 2026. Get the free weekly email to hear when one posts.

Proposed for fiscal 2027 (3 projects, $332,475)

State fiscal year: July 2026 to June 2027. Available formula funding for the year, per the plan: $278,709. Proposals can run well past that; some depend on special awards from the state.

ProjectDevelopmentTotal project cost
Vacant Unit Turnover OBR #214
Unit turnovers & renovations · special award requested: $23,152
Old Bass River Village$23,152
Vacant Unit Turnover WMV A Side #2-10
Unit turnovers & renovations · special award requested: $27,907
Windmill Village$27,907
ADA Vacant Unit Rehab Bldg. 2 Unit 12
Accessibility (ADA) · special award requested: $182,866
Center St Village$281,416

Proposed for fiscal 2028 (2 projects, $243,061)

State fiscal year: July 2027 to June 2028. Anticipated formula funding for the year, per the plan: $278,709. Proposals can run well past that; some depend on special awards from the state.

ProjectDevelopmentTotal project cost
Tree Trimming and Removal 667- /705
Paving, walkways & site
Center St Village$11,271
Building Envelope Upgrades Grassy Pond Dr. and Bayridge Dr.
Siding, masonry & exterior
$231,790

Proposed for fiscal 2029 (4 projects, $254,838)

State fiscal year: July 2028 to June 2029. Anticipated formula funding for the year, per the plan: $278,709. Proposals can run well past that; some depend on special awards from the state.

ProjectDevelopmentTotal project cost
Parking area repairs
Paving, walkways & site
Windmill Village$121,626
Crawlspace Access Hatch
Other
Special Needs Housing$11,720
Stormwater Drainage Mulhern Dr.
Paving, walkways & site
Mulhern Drive Family Housing$104,877
Storage Shed WMV
Other
Windmill Village$16,615

Further out: fiscal 2030–2031 (2 projects, $2,372,835)

The plan's “Years 4 and 5”: rough planning amounts, further out. State fiscal years: July 2029 to June 2031.

ProjectDevelopmentTotal project cost
Egress Balcony Replacement O.B.R.
Siding, masonry & exterior
Old Bass River Village$459,830
Siding & Window Replacement O.B.R. CPA
Windows & doors
Old Bass River Village$1,913,005

Active projects (18)

The plan's list of projects already under way: some in design or out to bid, some under construction or wrapping up. When one goes out to bid, the COMMBUYS title is sometimes just its FISH number.

ProjectDevelopmentTotal project cost
ARPA FF: Landscape Designing
FISH 075098
$14,572
AIP: 667 Routine Turnovers
FISH 075113
$24,800
New Septic System Center Street
FISH 075085
Center St Village$1,094,380
Install ADA automatic door
FISH 075086
Special Needs Housing$20,701
ARPA Targeted Award: Dennis Fed- Pac Panel and Fire Alarm Systems
FISH 075097
Center St Village$684,866
Mini-Split/ASHP for Community Room
FISH 075103
Old Bass River Village$12,886
Ellis Dr. Deck Replacement
FISH 075104
Scattered Site$71,763
Select Tree Trimming & Pruning 705/667
FISH 075106
Windmill Village$9,800
Common Area Flooring Replacement Clipper Ln.
FISH 075107
Special Needs Housing$74,563
Cast Iron Drain Line Replacement BLDG. 2
FISH 075109
Center St Village$39,027
Remaining Siding & Windows (Rear Upper Level)
FISH 075110
Windmill Village$102,382
Accessible unit conversion #9
FISH 075111
Center St Village$226,545
ADA Vacant Unit Rehab Unit #114 667-2
FISH 075114
Old Bass River Village$101,158
Siding, Windows & Door Replacement Crestwood Dr. and Ellis Dr.
FISH 075115
Scattered Site$289,985
Install Exit Signage - Center Street Village
FISH 075116
Center St Village$110,225
Door Closer Upgrade - Center Street Village
FISH 075117
Center St Village$81,394
EMG Air Conditioner Replacement Clipper Ln.
FISH 075118
Special Needs Housing$7,488
Mold Remediation & Plumbing Repairs
FISH 075119
Center St Village$6,869

Costs are total project costs (design and construction) as listed in the plan, read automatically from the PDF. The plans schedule work by the state's fiscal year (July to June), which can differ from an authority's own. Proposed projects are not funded until the state approves them, and plans change: costs rise, projects slip or get split into phases. Check the plan itself before relying on a number.