Open bids and the projects in this authority's capital plan, with costs. Bids come from COMMBUYS; projects come from the annual plan the authority files with the state.
None on COMMBUYS as of Sep 27, 2026. Get the free weekly email to hear when one posts.
This authority's newest plan on the state portal uses the state's previous format. “Spending planned” lists the state fiscal years (July to June) with money scheduled for each project; fiscal 2026 and earlier have already ended. “—” means the plan shows no spending scheduled for it in those years.
| Project | Development | Total cost | Spending planned |
|---|---|---|---|
| 2008 FF Master CFA FISH 043011 · Other | Colonial Park 667-01 | $3,000 | — |
| ARPA FF: AddiParking & Repaving 667-1 FISH 043050 · Paving, walkways & site | Colonial Park 667-01 | $76,898 | 2026 |
| Tub Surrounds 667-1 FISH 043051 · Kitchens & baths | Colonial Park 667-01 | $9,731 | 2026 |
| Select Flooring Replacement 667-1 FISH 043053 · Interiors, flooring & painting | Colonial Park 667-01 | $10,000 | 2026 |
| Countertop Replacement 2022 FISH 043055 · Kitchens & baths | Colonial Park 667-01 | $9,983 | 2026 |
| Water Heater Replacement 667-1 Electric not gas FISH 043058 · Heating, boilers & HVAC | Colonial Park 667-01 | $9,900 | 2026 |
| Hallway Heaters - Phase II FISH 043059 · Heating, boilers & HVAC | Colonial Park 667-01 | $9,900 | — |
| Selective Sidewalk Replacement 667-1 FISH 043060 · Paving, walkways & site | Colonial Park 667-01 | $40,242 | 2026 |
| Select Tree Removal FISH 043061 · Paving, walkways & site | Colonial Park 667-01 | $46,888 | 2026 |
| Greenhouse Repairs 667-1 FISH 043062 · Other | Colonial Park 667-01 | $9,749 | 2026 |
| Tub Surrounds - Phase II FISH 043063 · Kitchens & baths | Colonial Park 667-01 | $9,741 | 2026 |
| Countertop Replacement - Phase II FISH 043064 · Kitchens & baths | Colonial Park 667-01 | $9,983 | 2026 |
| Replace Exterior Hose Bibbs FISH 043065 · Siding, masonry & exterior | Colonial Park 667-01 | $9,750 | 2027 |
| Community Room Code Compliance FISH 043067 · Interiors, flooring & painting | Colonial Park 667-01 | $17,710 | 2026 |
| Select Flooring Replacement - Phase II FISH — · Interiors, flooring & painting | Colonial Park 667-01 | $10,000 | 2026 |
| Cabinet Refacing FISH — · Kitchens & baths | Colonial Park 667-01 | $45,375 | 2027 |
| Select Siding - Phase II FISH — · Siding, masonry & exterior | Colonial Park 667-01 | $27,225 | 2028 |
| New gutters and leaf guards FISH — · Roofing & gutters | Colonial Park 667-01 | $24,956 | 2029–2030 |
| Exterior Lighting FISH — · Electrical & generators | Colonial Park 667-01 | $27,130 | 2027–2028 |
| Select Patio Repairs FISH — · Other | Colonial Park 667-01 | $23,520 | 2029 |
Costs are total project costs (design and construction) as listed in the plan, read automatically from the PDF. The plans schedule work by the state's fiscal year (July to June), which can differ from an authority's own. Proposed projects are not funded until the state approves them, and plans change: costs rise, projects slip or get split into phases. Check the plan itself before relying on a number.