Open bids and the projects in this authority's capital plan, with costs. Bids come from COMMBUYS; projects come from the annual plan the authority files with the state.

Open bids

None on COMMBUYS as of Sep 27, 2026. Get the free weekly email to hear when one posts.

Projects in its capital plan (27, $1,562,007 total cost)

This authority's newest plan on the state portal uses the state's previous format. “Spending planned” lists the state fiscal years (July to June) with money scheduled for each project; fiscal 2026 and earlier have already ended. “—” means the plan shows no spending scheduled for it in those years.

ProjectDevelopmentTotal costSpending planned
2008 FF Master CFA
FISH 021013 · Other
Grandview Terrace 667-02$9,250—
FF: Automatic door opener Buiding 1
FISH 021049 · Windows & doors
Grandview Terrace 667-02$3,1502026
Energy Efiicient lighting upgrade
FISH 021055 · Electrical & generators
Grandview Terrace 667-02$1,0002026
Covid-19 Office Adaptation: Barre
FISH 021065 · Other
Grandview Terrace 667-01$10,0002026
Unit Renovations
FISH 021066 · Unit turnovers & renovations
Grandview Terrace 667-01$12,1082026
ARPA Targeted Award: Barre Federal Pacific Electrical Panel Replacements
FISH 021067 · Electrical & generators
667-1A, 667-01-001, 667-01-002, 667-01-003, 667-01-004, 667-01-005$288,4112026
ARPA FF: Laundry room upgrades
FISH 021070 · Other
Grandview Terrace 667-01$11,2402026
Kitchen upgrades (on turnover) - Phase 3
FISH 021071 · Kitchens & baths
Grandview Terrace 667-01$9,9662026
Faucet Replacements
FISH 021072 · Other
Grandview Terrace 667-01$9,9712026
Shed Removal/Replacement
FISH 021073 · Other
Grandview Terrace 667-01$9,8762026
NCSR Recapitalization Award
FISH 021074 · Other
Bradford Apts 705-01$983,4802026–2027
VCT flooring replacement building 2
FISH 021075 · Interiors, flooring & painting
Grandview Terrace 667-01$24,8892026
Smoke Detector Replacement
FISH 021076 · Fire alarm & sprinklers
Grandview Terrace 667-01$9,5792026
Component Replacement on Turnover
FISH 021077 · Unit turnovers & renovations
Grandview Terrace 667-01$13,4402026
Site Improvements
FISH 021078 · Paving, walkways & site
Grandview Terrace 667-01$9,5792026
Select Trim Replacement Phase 2
FISH 021080 · Siding, masonry & exterior
Grandview Terrace 667-01$9,9662026
Security Camera Upgrades Phase 1
FISH 021081 · Security & access
Grandview Terrace 667-01$9,5792026
Bathtub Upgrades
FISH 021082 · Other
Grandview Terrace 667-01$9,8812026
667-1 Lot Survey
FISH 021083 · Studies & design
Grandview Terrace 667-01$9,8202026
Kitchen cabinet replacement, GFCI upgrade
FISH 021084 · Kitchens & baths
Bradford Elderly Apartments 667-1A$5,8992026
Paving Upgrades (Upper Lot)
FISH — · Paving, walkways & site
Grandview Terrace 667-01$49,9132026
Security Camera Upgrades Phase 2
FISH — · Security & access
Grandview Terrace 667-01$9,8152026
Lock Replacement
FISH — · Security & access
Grandview Terrace 667-01$11,7962026
Component Replacement on Turnover
FISH — · Unit turnovers & renovations
Grandview Terrace 667-01$9,9562026
Building #3 Ceiling Repairs
FISH — · Interiors, flooring & painting
Grandview Terrace 667-01$9,9832027
Select Trim Replacement Ph 3
FISH — · Siding, masonry & exterior
Grandview Terrace 667-01$9,8812026
Community Rm Upgrades
FISH — · Other
Grandview Terrace 667-01$9,5792026

Costs are total project costs (design and construction) as listed in the plan, read automatically from the PDF. The plans schedule work by the state's fiscal year (July to June), which can differ from an authority's own. Proposed projects are not funded until the state approves them, and plans change: costs rise, projects slip or get split into phases. Check the plan itself before relying on a number.